The Hon’ble Supreme Court of India (“Supreme Court”) vide its judgment dated May 7, 2024 in the case titled National Highway Authority of India v. Meissners Hindustan Construction Company Limited (Civil Appeal No. 4702 of 2023) has held that the Court under Section 34 of the Arbitration & Conciliation Act, 1996 (“Act”) cannot interfere with the Arbitral Tribunal’s interpretation of a contract.
Brief Facts
The Appellant in the present case, National Highways Authority of India Limited ("NHAI") on June 2, 2004 awarded a contract to the Respondent i.e., Meissners Hindustan Construction Company Limited for the work of Allahabad Bypass Project which involved the construction of a road from km 158 (one hundred and fifty eight) to km 198 (one hundred and ninety eight). The total cost of the project was Rs. 4,46,99,12,839/- (Rupees four hundred forty-six crores ninety-nine lakhs twelve thousand eight hundred thirty-nine). Thereafter, certain disputes arose between the parties and the matter was ultimately referred to the Arbitral Tribunal. The three claims before the Arbitral Tribunal were as follows:
The award passed by the Ld. Arbitral Tribunal
The Arbitral Tribunal passed its award on March 30, 2010, on three distinct claims that were presented during the arbitration:
Challenge to the arbitral award under Section 34 of the Act
The Appellant, being aggrieved by the award, filed a petition under Section 34 of the Act before the Ld. Single Judge of the Hon’ble High Court of Delhi. The Ld. Single Judge vide Judgment/ Order dated November 30, 2011, confirmed the award with respect to the Claim No. 1 and Claim No. 3, relying upon the decision in the case of National Highways Authority of India v. Meissners ITD Cementation India Limited, 2008 (100) DRJ 431. However, with respect to the Claim No. 2, the Ld. Single Judge held that the award was a majority decision of the Arbitral Tribunal based on an analysis of the material placed before the Arbitral Tribunal. Therefore, the award for Claim No. 2 was upheld.
Appeal under Section 37 of the Act
The Appellant, once again being aggrieved, preferred an appeal under Section 37 of the Act before a Division Bench of the Hon’ble High Court of Delhi. By the impugned judgment, the appeal preferred by the appellant was dismissed. Therefore, being aggrieved by the Arbitral Tribunal’s award and the judgments of the High Court, the appellant preferred the present appeal before the Hon’ble Supreme Court.
Submissions of the Parties
The Appellant’s Submissions
The Respondent’s Submissions
Consideration of submissions by the Supreme Court
The Hon’ble Supreme Court noted that the Court is dealing with concurrent findings arrived at by the Arbitral Tribunal, the learned Single Judge in a petition under Section 34 of the Act, and the Division Bench in appeal under Section 37 of the Act and is concerned with the construction of the terms of a contract between the parties in terms of the Appeal under Section 37 of the Act.
The Hon’ble Supreme Court noted the various precedents on the scope of interference with an Arbitral Award and referred to the case of Parsa Kente Collieries Ltd. v. Rajasthan Rajya Vidyut Utpadan Nigam Limited, (2019) 7 SCC 236 and MMTC v. Vedanta Limited, (2019) 4 SCC 163 to note that the Court does not sit in appeal over the Arbitral aware and may interfere on merits on the limited ground provided under Section 34 (2)(b)(ii) of the Act i.e., if the award is against the public policy of India.
Further, the Hon’ble Supreme Court referred to the case of UHL Power Company Ltd. v. State of Himachal Pradesh, (2022) 4 SCC 116 wherein it was held that the jurisdiction of the Court under Section 34 is relatively narrow and the jurisdiction of the Appellate Court under Section 37 of the Arbitration Act is all the more circumscribed. Therefore, the Hon’ble Supreme Court in the present case observed that the Court will deal with the submissions in light of the limited scope for interference.
Decision of the Supreme Court
The Supreme Court noted that the Division Bench held that the imposition of a tax or upward revision of an already existing tax or levy through subsequent legislation is admittedly akin to the levy of additional royalty. Further, the Supreme Court noted that the decision of the High Court in the case of National Highways Authority of India v. Meissners ITD Cementation India Limited has been confirmed by the Supreme Court vide order dated April 24, 2015 with a partial modification. The issue in the said judgment was also regarding a claim based on an upward revision of royalty. Further, it was noted that the Clauses 70 to 70.8 of the agreements are identical and the arguments led are also the same.
The Supreme Court further on the issue of whether the claim for the construction of embankment forms part of the activity of clearing and grubbing and was not payable as embankment work, observed that two expert members of the Arbitral Tribunal held in favor of the respondent, whereas the third member dissented.
The Supreme Court therefore noted that dispute that as far as the construction of the terms of a contract is concerned, it is for the Arbitral Tribunal to adjudicate upon. If, after considering the material on record, the Arbitral Tribunal takes a particular view on the interpretation of the contract, the Court under Section 34 does not sit in appeal over the findings of the arbitrator.
The Supreme Court also observed that the Division Bench was right in holding that the majority opinion of technical persons need not be subjected to a relook, especially when the learned Single Judge had also agreed with the view taken by the Arbitral Tribunal. Therefore, in light of the aforesaid, the Supreme Court found nothing perverse or illegal about the award and consequently, the appeal was dismissed.
Conclusion and analysis
The above judgment emphasizes the Hon’ble Supreme Court's adherence to the principle of limited judicial interference in arbitral awards under the Act. The Court in the judgment has reiterated that the grounds for challenging an arbitral award are restricted to instances of contravention of substantive Indian law, violations of the Act, or breaches of contract terms, emphasizing the concept of "patent illegality". The Court further has emphasized the narrow scope of the Court's jurisdiction under Section 34 of the Act, highlighting that the appellate court's powers under Section 37 are even more constrained. This case highlights the importance of upholding arbitral awards unless they violate public policy or exhibit clear legal errors, as established by previous judicial precedents such as UHL Power Company Ltd. v. State of Himachal Pradesh and NHAI v. ITD Cementation (India) Ltd. The judgment upholds the principle of limited judicial interference in arbitral awards, respecting the autonomy of arbitrators in interpreting contractual terms and the limited role of courts in reviewing arbitral decisions.
Please find attached a copy of the judgement here.
This update has been contributed by Namitha Mathews (Partner) and Pragalbh Bhardwaj (Senior Associate).
Argus Knowledge Centre is now on WhatsApp! Send us a message on +91 8433523504 to receive updates from our Knowledge Centre.
7A, 7th Floor, Tower C, Max House,
Okhla Industrial Area, Phase 3,
New Delhi – 110020
The rules of the Bar Council of India do not permit advocates to solicit work or advertise in any manner. This website has been created only for informational purposes and is not intended to constitute solicitation, invitation, advertisement or inducement of any sort whatsoever from us or any of our members to solicit any work in any manner. By clicking on 'Agree' below, you acknowledge and confirm the following:
a) there has been no solicitation, invitation, advertisement or inducement of any sort whatsoever from us or any of our members to solicit any work through this website;
b) you are desirous of obtaining further information about us on your own accord and for your use;
c) no information or material provided on this website is to be construed as a legal opinion and use of this website will not create any lawyer-client relationship;
d) while reasonable care has been taken in ensuring the accuracy of the contents of the website, Argus Partners shall not be responsible for the results of any actions taken on the basis of information provided in this website or for any error or omission in the website; and
e) in cases where the user has any legal issues, the user must seek independent legal advice.